Hello and thank you for visiting our Prospect Bay tower project update page. This is the primary and most up-to-date source of information for progress on the Prospect Bay tower. We will update this page any time we have new information about the tower’s estimated on-air date. We also provide these updates on our social media platforms: Twitter, Facebook, and LinkedIn.
Tuesday, March 24, 2020:
Calvert Crossland recently visited the proposed site at the Prospect Bay Country Club along with a team of environmental consultants to discuss and map out the best location for the tower.
Monday, April 14, 2021:
This site is presently on hold.
Wednesday, January 11, 2023:
We are seeing interest in this site from carriers! There is a kick-off conference call scheduled for January 16, 2023 and we hope to be moving forward. Stay Tuned!
Wednesday, March 8, 2023:
Community Outreach Meeting was held to discuss the project with the Prospect Bay Country Club Community
Friday, April 14, 2023:
To demonstrate the visual impact of a telecommunications tower, on Friday, April 14th, a balloon fly will take place near the proposed new tower location from 10 AM to 1 PM. Please feel free to join us in the cul-de-sac at the end of Fairway Island, off Hole 11, where members of our team will be on hand to answer any questions. If the weather prevents a successful test from happening, we have selected Monday, April 17th as our “rain date.”
Wednesday, October 18, 2023:
Calvert Crossland is currently putting together a Conditional Use application to go before the County. Hope to have this completed by the end of the year. The hope is to construct the tower in the Spring of 2024.
Wednesday, February 21, 2024:
The proposed Prospect Bay cell tower received a Conditional Use approval by the Queen Anne’s County Board of Zoning Appeals on February 21st, 2024. We are currently completing the requirements to file for a Building Permit and ordering the tower manufacturers to begin fabrication of the tower. The forecasted date to commence construction should be within the first 2 weeks of June 2024. The estimated time of construction is 6 weeks, weather permitting. Calvert Crossland forecasts Verizon Wireless fiber circuit and service to be available Late Fall of 2024. We continue to reach out to AT&T and T-Mobile to interest them in locating on the tower.
Wednesday, April 10, 2024:
Received the Conditional Use Approval letter from the County.
Friday, May 31, 2024:
Geo-Tech and Structural Design reports have been received and the building permit is about to be submitted!
Tuesday, July 23, 2024:
Building and Grading Permits have been approved and received. Could see foundation being poured as early as next week!
Click here to see the proposed site location!
Thursday, September 12, 2024:
The tower has been stacked! It will still take many months to get the carriers on the tower, but we can see the finish line!